9 min read
Tether’s failed Uruguay project could expose a bigger problem with Bitcoin mining costs, but the $120 million loss was not caused by mining economics alone. A power contract dispute triggered the project’s collapse, while wider industry data shows miners are operating with increasingly sensitive cost structures.
Tether entered Uruguay expecting renewable electricity, a dependable grid, and room to expand its mining operation. Instead, uncertainty over electricity capacity became serious enough to help derail two sites that were originally intended to support a broader South American strategy.
The bigger lesson reaches beyond Tether. Electricity prices, network competition, aging machines, infrastructure costs, and growing demand from AI companies are changing what it takes to run a profitable Bitcoin mine.

Tether’s Uruguay project primarily collapsed because the company and state utility UTE disagreed over electricity supply. The dispute eventually left the mining facilities without the dependable power capacity needed to keep expanding.
Tether announced its move into Uruguay in 2023 and described the country as an attractive location for sustainable Bitcoin mining. A former contractor later estimated that Tether had invested about $60 million in each of two sites, putting the total near $120 million.
The central disagreement concerned how the electricity contract should be interpreted. Tether reportedly viewed its allocated power as a minimum that could increase, while UTE considered the agreed amount a maximum limit.
That difference became critical as the mining operation needed more electricity. According to Reuters, the facilities sometimes lacked enough power for days, which limited their ability to operate as planned.
The relationship deteriorated further after Tether’s local entity stopped paying electricity bills and moved to terminate the contracts. UTE eventually cut electricity to the sites in July 2025, and Tether later ended operations and reduced its local workforce.
This makes the Uruguay failure more complicated than a simple case of Bitcoin becoming too expensive to mine. Still, the project shows why electricity contracts can determine whether a large mining investment produces returns or becomes an expensive stranded asset.
Fun fact: The conflict centered on interpretation: Tether and a former contractor read the contracted electricity figure as a minimum baseline that could be scaled up as the facilities expanded.
Reliable and affordable electricity matters more to Bitcoin miners than simply having access to renewable energy. A green power grid does little for mining economics if electricity is expensive, limited, or unavailable when thousands of machines need it.
Uruguay initially appeared attractive because renewable sources provide most of the country’s electricity. Yet renewable power and low-cost power are not the same thing, especially for an industrial user that operates equipment around the clock.
Bitcoin mining is unusually dependent on electricity because specialized computers perform nonstop calculations to compete for block rewards. Cambridge researchers found electricity represents more than 80% of miners’ cash-based operating expenses.
The same Cambridge study reported a median electricity cost of about $45 per megawatt hour among surveyed miners. The median rose to $55.50 per megawatt hour when other related power costs were included.
Those numbers explain why a disagreement over available megawatts can become an existential issue rather than a routine contract problem. A mining company must know how much power it can receive, what that power costs, and whether access will remain dependable.
For miners, an attractive energy source is therefore only part of the calculation. Contract terms, grid capacity, operating hours, and future pricing can matter just as much as whether the electricity comes from wind, hydro, solar, or fossil fuels.

Yes, the 2024 Bitcoin halving continues to shape mining economics because it reduced the number of new Bitcoins awarded for each block. Miners must now compete for smaller block rewards while continuing to pay electricity and infrastructure expenses.
Bitcoin’s halving mechanism is built into the network and cuts the block subsidy roughly every four years. The April 2024 event reduced the reward from 6.25 Bitcoin to 3.125 Bitcoin for each block.
A miner can offset that reduction if Bitcoin’s price rises enough or if its own costs fall sharply. Problems appear when prices weaken, network competition rises, or electricity expenses increase before revenue can catch up.
Public miner MARA provides a useful example of that pressure. Its purchased electricity cost per Bitcoin at owned sites increased to $38,690 in the second quarter of 2026 from $33,735 a year earlier.
MARA said the increase reflected higher power costs and global network difficulty growing faster than its own mining capacity. This happened even though its cost per unit of computing power improved by about 4%.
That distinction matters for understanding Tether’s situation. A mining site facing uncertain electricity supply is operating in a market where every interruption can become more costly because competition for the remaining Bitcoin rewards continues regardless.
Better machines reduce electricity used for each unit of computing power, but they cannot eliminate competition from the rest of the Bitcoin network. When global computing capacity rises, each miner must work harder to capture the same limited rewards.
Cambridge estimated that industry-wide mining hardware efficiency improved about 24% year over year, reaching roughly 28.2 joules per terahash. Despite that progress, estimated Bitcoin mining electricity use still increased because total network computing power continued growing.
This creates a treadmill effect for miners. One company can replace older machines with more efficient models, only to see rivals do the same and push network difficulty higher.
Mining revenue per unit of computing power provides another way to see the pressure. Luxor reported Bitcoin hash price at about $31.73 per petahash per day on August 10, 2026.
The same data showed a large difference between efficient and older equipment. Fleets operating below 14 joules per terahash generated far more revenue per unit of electricity than machines using 25 to 38 joules per terahash.
That means efficiency has become necessary just to remain competitive, rather than guaranteeing strong profits. Miners must continuously invest in machines while knowing that industry-wide upgrades can quickly reduce the advantage they hoped to gain.
Fun fact: The disagreement revolved around the interpretation of electricity capacity terms, with Tether seeing it as a minimum and UTE as a maximum.
Yes, electricity costs can understate how expensive Bitcoin production really is because mining machines wear out and facilities require maintenance. Labor, cooling, repairs, property expenses, financing, and equipment depreciation can significantly raise the final cost.
This distinction matters when articles describe a miner’s production cost using electricity alone. The cash needed to keep machines running is important, but it does not capture the money spent replacing equipment that loses value quickly.
Riot Platforms illustrates the gap clearly. In the first quarter of 2026, Riot reported an average cost of $44,629 per Bitcoin excluding miner depreciation.
When miner depreciation was included, Riot’s reported cost rose to $96,283 per Bitcoin. The production value of each Bitcoin mined during that quarter was about $75,964, showing how different the economics can appear once equipment costs are counted.
Riot also listed compensation, insurance, repairs, ground rent, water, and property taxes among its mining expenses. Those items show why comparing Bitcoin’s market price only with a miner’s electricity bill can create an incomplete picture.
For Tether, a $120 million site investment involved more than purchasing electricity and collecting Bitcoin. Infrastructure must remain productive long enough to recover its construction and equipment costs, which becomes harder when power access itself is uncertain.

AI could create a bigger challenge because miners now have another possible use for valuable power and data center infrastructure. The question is becoming whether Bitcoin mining is still the best use of every available megawatt.
Bitcoin miners have spent years securing land, grid connections, substations, cooling systems, and large electricity contracts. Many of those same assets are increasingly valuable to companies building AI and high-performance computing infrastructure.
Riot is already showing how that transition can work. The company reported $33.2 million in data center revenue during the first quarter of 2026 while continuing its Bitcoin mining operations.
That creates an opportunity cost that did not exist at the same scale during earlier Bitcoin cycles. A company with scarce power capacity can compare expected mining income with longer and potentially steadier revenue from data center customers.
Tether itself has not abandoned mining and is still investing in ways to reduce operating costs. In April, it announced modular mining systems designed to improve control over energy use, cooling, upgrades, efficiency, and performance.
The Uruguay failure therefore does not show that Bitcoin mining is finished. It shows that mining has become an increasingly demanding infrastructure business where cheap power, secure contracts, efficient equipment, and the alternative value of electricity can decide whether a major investment survives.
This article was made with AI assistance and human editing.
If you liked this, you might also like:
We appreciate you taking the time to share your feedback about this page with us.
Whether it's praise for something good, or ideas to improve something that
isn't quite right, we're excited to hear from you.
Lucky you! This thread is empty,
which means you've got dibs on the first comment.
Go for it!